CONSTRUCTION
process
Copyright © 1990 - 2014 All rights reserved
DAY 1
START AT 11h00
moladi formwork is delivered to site Area = 74m² Mass = 550kg Volume = 4m³ moladi formwork panels are assembled by unskilled labourers to form the mould panels of the desired house plan
STEP 1
Internal formwork panels are erected Window frames and block-outs are positioned within the wall cavity Reinforcing bars are positioned within the cavity to engineer specifications
STEP 2
Door frames and block-outs are positioned within the wall cavity External formwork panels are erected to close off the wall cavity Erection is completed in 4 hours with 4 unskilled labourers
STEP 3
The wall cavity is filled with 4m³ of moladi aerated mortar by unskilled labourers The pour is completed in 2 hours with 4 unskilled labourers
STEP 4
FINISH AT 17h00
DAY 2
moladi formwork panels are removed moladi formwork panels are completely removed in 2 hours with 4 unskilled labourers
STEP 1
Immediately after the formwork panels are removed, the walls are painted with a cementitious water based paint Oil or acrylic based paints can be applied after the walls have cured, or in 28 days
STEP 2
The engineer certified roof is installed The windows and doors are installed Final finishings, such as sanitary ware and lighting are completed The structure is now ready for occupation
STEP 3
START AT 07h00
FINISH AT 17h00